Client / Site | Cargill |
Location | Borg el Arab, Alexandria, Egypt |
Client’s need / Requirements |
Upgrade existing City water treatment plant |
Project |
-Replacement of existing pretreatment system with two ultrafiltration modules and design, commissioning & startup of new RO WTP -The new UF modules has to be installed at the same place of existing Pre-treatment units without shutting the plant down for longer than one hour. -Capacity of 3360 m3/day Ultrafiltration system., 600 m3/day RO system. |
Objective | The new system was able to: • Enhance aeration efficiency. • Save energy. • Reduced carbon emissions. • Lower maintenance cost. |